Scoping
Process |
Spring
2002 |
| Conceptual Engineering/Project
Description |
Spring 2002
Summer 2004 |
| Preliminary
Engineering |
2005 – 2006 |
| Supplemental Draft EIS/Subsequent Draft EIR
|
February 2007 |
| Public
Hearing |
March 2007 |
| Supplemental Final EIS/Subsequent Final EIR Certfied
by RT |
Late Spring 2007 |
| |
FTA
Record of Decision |
Summer 2007 |
| |
Construction |
2008/2010 |